Summary of significant progress includes:
Mechanical, Electrical and Plumbing rough-in with the needed modifications got completed, inspected, and passed
Grease trap got installed and inspected
Propane gas pipes re-routed to combine the two tanks
Network CAT6 cables installed
Pre drywall inspection passed; insulation for sound reduction; drywall installation started
Summary of significant progress includes:
North exterior face progressed, concrete at entrance poured
Interior wall framing started
Interior details and bids reviewed for flooring and other trades
Mechanical, electrical and plumbing rough-in started
Started selections of the fixtures and other details
Exterior door openings had to be resized; completed
Architectural and professional services for the interior plan details including kitchen and mezzanine areas
Finalized interior framing details after on-site review; picked a subcontractor for framing
Connected the two buildings’ walls
Summary of significant progress includes:
Plumbing rough-in with some modifications completed and inspected
Mechanical rough-in inspection revealed fire-damper needs; it required an update to the architectural drawing and submission; completed
New Propane tank installed and connected; heating started for the winter
Interior wall framing changes at the fire-rated wall completed; backing boards in progress
Site grading and clean up; exterior doors got painted
Summary of significant progress includes:
North exterior face progressed, concrete at entrance poured
Interior wall framing started
Interior details and bids reviewed for flooring and other trades
Mechanical, electrical and plumbing rough-in started
Started selections of the fixtures and other details
Exterior door openings had to be resized; completed
Architectural and professional services for the interior plan details including kitchen and mezzanine areas
Finalized interior framing details after on-site review; picked a subcontractor for framing
Connected the two buildings’ walls
Summary of significant progress includes:
Pre-engineered metal building construction about 98% completed
Exterior concrete stoop and pads poured across the entry and exit doors
Architectural and professional services for the interior plan details including doors and framing
Received and reviewed proposals for the exterior and interior doors
Received and reviewed proposals for the interior framing and other trades
Connected the addition building’s roof with the existing roof; drainage re-routed
Summary of significant progress includes:
Pre-engineered metal building construction about 98% completed
Exterior concrete stoop and pads poured across the entry and exit doors
Architectural and professional services for the interior plan details including doors and framing
Received and reviewed proposals for the exterior and interior doors
Received and reviewed proposals for the interior framing and other trades
Connected the addition building’s roof with the existing roof; drainage re-routed
Summary of significant progress includes:
Engineering, architectural, and professional services and project plan details
Sitework with underground drainage
Electrical and plumbing utility layout
Concrete footing and slab
Pre-engineered metal building construction
Detailed specifications and proposals for additional trades
Challenge encountered:
Distant bathroom drain could not be connected to the existing septic tank; a new septic tank needed to be installed with some onsite changes and quick decisions; county office approved the new setup.
Summary of significant progress includes:
Engineering, architectural, and professional services and project plan details
Sitework with underground drainage
Electrical and plumbing utility layout
Concrete footing and slab
Pre-engineered metal building construction
Detailed specifications and proposals for additional trades
Challenge encountered:
Distant bathroom drain could not be connected to the existing septic tank; a new septic tank needed to be installed with some onsite changes and quick decisions; county office approved the new setup.